Song Open Stadium Upgrade 57% Complete, First Phase on Track for November 2025

Song Open Stadium Upgrade 57% Complete, First Phase on Track for November 2025

SONG — The first phase of the Song Open Stadium upgrading project has reached 57.54% completion and remains on schedule, with full completion expected by 24 November 2025.

State Assemblyman for Bukit Semuja, John Ilus, said the renovation work includes several key upgrades such as:

  • Replacement of the grandstand roof
  • New spectator seats
  • Renovated toilets, VIP rooms, waiting rooms, staff offices, stores, and technical rooms
  • Full repainting of the stadium complex

“This stadium is a key facility for the people of Song, providing space for sports and recreational activities. Once completed, it will greatly benefit the local community,” he said during a working visit to the project site on Tuesday.

John also noted that the visit served as a reference for best practices in planning the upcoming Serian Stadium upgrade.

The first phase further includes enhancements to the sports infrastructure such as:

  • Upgraded football field and running track
  • Facilities for long jump, shot put, discus, high jump
  • Field drainage system
  • Construction of a rubber safety wall

The RM4.8 million project, which began on 25 November 2024, is being undertaken by Fias Enterprise with a 12-month implementation period.

Looking ahead, Phase Two will include the installation of recessed lighting, construction of a stadium fence, and parking facilities, aimed at delivering a complete and comfortable sports venue for the people of Song.

Also present during the visit were Katibas Assemblyman Lidam Assan and other distinguished guests.